Meeniyan Community Hub
Completed in Gippsland, the Meeniyan Community Centre applied lessons from earlier commercial hempcrete projects, combining cast-in-place walls with the first commercial use of RespiraBlocks to deliver a more efficient civic build.

Meeniyan Community Hub
Completed in Gippsland, the Meeniyan Community Centre applied lessons from earlier commercial hempcrete projects, combining cast-in-place walls with the first commercial use of RespiraBlocks to deliver a more efficient civic build.

Meeniyan Community Hub
Completed in Gippsland, the Meeniyan Community Centre applied lessons from earlier commercial hempcrete projects, combining cast-in-place walls with the first commercial use of RespiraBlocks to deliver a more efficient civic build.
Project Overview
The Meeniyan Community Centre brought hempcrete back into a civic setting, this time within a small regional town where the building is used daily for meetings, events, and community gatherings. Building on the experience gained at Mildura, the project combined cast-in-place hempcrete with the first commercial use of RespiraBlocks, testing how hemp systems could be delivered more efficiently within a public construction programme.
Project Overview
The Meeniyan Community Centre brought hempcrete back into a civic setting, this time within a small regional town where the building is used daily for meetings, events, and community gatherings. Building on the experience gained at Mildura, the project combined cast-in-place hempcrete with the first commercial use of RespiraBlocks, testing how hemp systems could be delivered more efficiently within a public construction programme.
Project Overview
The Meeniyan Community Centre brought hempcrete back into a civic setting, this time within a small regional town where the building is used daily for meetings, events, and community gatherings. Building on the experience gained at Mildura, the project combined cast-in-place hempcrete with the first commercial use of RespiraBlocks, testing how hemp systems could be delivered more efficiently within a public construction programme.
Project Details
Location & Project Size:
Meeniyan, Gippsland VIC - 150 m²
Built By
TS Constructions
Completion Year
2025
Designed By
Public Realm Lab
Materials Used
Cast & Block, RespiraBlock 80mm + RespiraCast
Supplied By
Respirabuilt
Project Details
Location & Project Size:
Meeniyan, Gippsland VIC - 150 m²
Built By
TS Constructions
Completion Year
2025
Designed By
Public Realm Lab
Materials Used
Cast & Block, RespiraBlock 80mm + RespiraCast
Supplied By
Respirabuilt
Project Details
Location & Project Size:
Meeniyan, Gippsland VIC - 150 m²
Built By
TS Constructions
Completion Year
2025
Designed By
Public Realm Lab
Materials Used
Cast & Block, RespiraBlock 80mm + RespiraCast
Supplied By
Respirabuilt
01
The Challenge
The Community Centre needed to perform as a heavily used public building within a compact regional town centre. Boundary conditions, including a neighbouring building within close proximity, introduced fire considerations, while internal areas such as public toilets required durability against moisture, impact, and daily cleaning. At the same time, the hempcrete installation needed to integrate smoothly within a commercial build schedule without extending programme timelines.
01
The Challenge
The Community Centre needed to perform as a heavily used public building within a compact regional town centre. Boundary conditions, including a neighbouring building within close proximity, introduced fire considerations, while internal areas such as public toilets required durability against moisture, impact, and daily cleaning. At the same time, the hempcrete installation needed to integrate smoothly within a commercial build schedule without extending programme timelines.
01
The Challenge
The Community Centre needed to perform as a heavily used public building within a compact regional town centre. Boundary conditions, including a neighbouring building within close proximity, introduced fire considerations, while internal areas such as public toilets required durability against moisture, impact, and daily cleaning. At the same time, the hempcrete installation needed to integrate smoothly within a commercial build schedule without extending programme timelines.
02
Our Approach
The wall system combined cast-in-place hempcrete with the first commercial use of RespiraBlocks. Introducing blocks in place of full-height formwork significantly reduced installation time compared to earlier projects. The hybrid method simplified sequencing, improved trade coordination, and allowed hempcrete to be delivered more efficiently within a commercial construction programme.
02
Our Approach
The wall system combined cast-in-place hempcrete with the first commercial use of RespiraBlocks. Introducing blocks in place of full-height formwork significantly reduced installation time compared to earlier projects. The hybrid method simplified sequencing, improved trade coordination, and allowed hempcrete to be delivered more efficiently within a commercial construction programme.
02
Our Approach
The wall system combined cast-in-place hempcrete with the first commercial use of RespiraBlocks. Introducing blocks in place of full-height formwork significantly reduced installation time compared to earlier projects. The hybrid method simplified sequencing, improved trade coordination, and allowed hempcrete to be delivered more efficiently within a commercial construction programme.
03
The Outcome
The completed building demonstrates that hempcrete can be delivered in civic architecture without extending construction time or relying on large specialist crews. The project received significant recognition at the 2025 ArchiTeam Awards, including the ArchiTeam Medal and the Community & Public Award, confirming that hemp-based systems can meet the durability, performance, and scheduling expectations of everyday community buildings.
03
The Outcome
The completed building demonstrates that hempcrete can be delivered in civic architecture without extending construction time or relying on large specialist crews. The project received significant recognition at the 2025 ArchiTeam Awards, including the ArchiTeam Medal and the Community & Public Award, confirming that hemp-based systems can meet the durability, performance, and scheduling expectations of everyday community buildings.
03
The Outcome
The completed building demonstrates that hempcrete can be delivered in civic architecture without extending construction time or relying on large specialist crews. The project received significant recognition at the 2025 ArchiTeam Awards, including the ArchiTeam Medal and the Community & Public Award, confirming that hemp-based systems can meet the durability, performance, and scheduling expectations of everyday community buildings.
More projects you might like
Discover other RespiraBuilt projects and see how our systems adapt to different styles, environments, and design visions.
More projects you might like
Discover other RespiraBuilt projects and see how our systems adapt to different styles, environments, and design visions.
More projects you might like
Discover other RespiraBuilt projects and see how our systems adapt to different styles, environments, and design visions.

Barn Style Shed House
Hempcrete block shed house on a high-fire coastal site.

Barn Style Shed House
Hempcrete block shed house on a high-fire coastal site.

High hemp walls for an owner builder
Cast & Block hybrid for 4m high owner-builder hempcrete home.

High hemp walls for an owner builder
Cast & Block hybrid for 4m high owner-builder hempcrete home.

Meeniyan Community Hub
Faster hempcrete delivery in a civic building.

Meeniyan Community Hub
Faster hempcrete delivery in a civic building.